Your 16-Week Tenant Improvement Timeline: From Lease to Move-In
Project Management
January 22, 2025
Adam Powell

Your 16-Week Tenant Improvement Timeline: From Lease to Move-In

A tenant improvement (TI) timeline is the most underestimated part of a commercial relocation. Sales teams promise "8 to 10 weeks"; reality lands at 14 to 18. Here's a realistic 16-week TI timeline that survives contact with actual construction.

Weeks 1-2: Planning and Programming

Engage architect and project manager. Conduct space programming with stakeholders. Confirm headcount, departmental adjacencies, conference and collaboration needs. Establish budget envelope and schedule constraints.

Weeks 3-4: Schematic Design

Architect produces test fits and preliminary floor plans. PM and client review against business goals. Iterate. Lock in the final concept.

Weeks 5-6: Design Development

Architect develops detailed plans: power, data, mechanical, plumbing, finishes, millwork. Furniture vendor begins space planning. Long-lead FF&E identified and quoted.

Weeks 7-8: Construction Documents and Bidding

Architect issues construction documents. PM issues competitive bid package to qualified general contractors (typically 3-5). GCs walk the space, submit pricing, and answer clarification rounds.

Week 9: GC Award and Permitting

PM and client evaluate bids on price, schedule, and qualifications. Award contract. Submit permit applications. Long-lead FF&E orders placed.

Weeks 10-13: Construction

Demolition, MEP rough-in, framing, drywall, finishes. Weekly OAC (owner/architect/contractor) meetings. PM tracks budget, schedule, change orders, and quality. Furniture installation begins toward end of construction.

Weeks 14-15: Substantial Completion and Punch List

GC achieves substantial completion. PM walks space with client, architect, and GC; documents punch list. Final cleaning. IT install (data, AV, security).

Week 16: Move and Occupancy

Weekend move-in. Day 1 triage to resolve workspace issues. Building orientation for employees. Celebrate.

Where Schedules Break

The most common slip points: permit delays (add 2-4 weeks if not anticipated), long-lead millwork or custom furniture, MEP coordination conflicts, and late-stage scope changes. A disciplined PM mitigates all four.

Get a realistic schedule built for your specific project.

About the Author

A

Adam Powell

CIG Consulting Team

Expert in commercial project management, delivering insights from years of experience in the Atlanta market.

Need Expert Advice?

Contact our team to discuss how these insights apply to your specific project needs.